Core Training for Microsoft Office Project 2003

Setting Up Resources

Setting Up People Resources

1To set up the initial list of resources, in the Project Guide toolbar, click Resources, and in the Resources pane, click the Specify people and equipment for the project link.
2Notice that the Project Guide: Simple Resource Sheet view replaces the Gantt Chart view. To continue, in the Specify Resources pane, click Enter resources manually, and then click Done.
3To enter the resources' names, in the Resource Sheet view, click the first cell under Resource Name, and for the purposes of this exercise, press SPACEBAR, wait as the name is typed for you, and then press ENTER.
4Notice that Project numbers this resource as 1. To assign eight more resources to this project, press SPACEBAR, wait as the names of the resources are typed for you, and then press ENTER.
5To close the Project Guide so you can see more of the Resource Sheet, click the Show/Hide Project Guide button, as indicated.
6To switch to the Resource Sheet view and add more resource information, on the View menu, click Resource Sheet.
7To enter the name of a resource by category, click in the Resource Name field below Brenda Diaz, press SPACEBAR, and wait as the resource name is typed for you.
8To change the Max. Units setting of the Electrician resource, press TAB until you reach the Max. Units column, and then click the Up arrow in the Max. Units box until 200% is displayed.
9To indicate that Jan Miksovsky will be working half time on this project, click the Max. Units field for Jan Miksovsky, and click the Down arrow one time so that 50% displays.
10To enter the pay rate for a resource, click the Std. Rate field for the resource Garrett R. Vargas, press SPACEBAR, wait as the rate is typed for you, and then press ENTER.
11To enter the pay rates for the other nine resources, press SPACEBAR, wait as the rates are typed for you, and then press ENTER.
12To remove a resource already assigned, click Brenda Diaz in the Resource Name field, press DELETE, and then, in the Indicator field in the first column, click the Delete indicator.
13To delete the entire row and renumber the subsequent resources, in the drop-down list, click Delete the entire resource.

Setting Up Equipment and Material Resources

1To begin setting up equipment resources, in the Resource Name column of the Resource Sheet view, click the empty cell below Electrician.
2To continue, on the Standard toolbar, click the indicated Resource Information button.
3To enter the resource name, for the purposes of this exercise, press SPACEBAR, and the text will be typed for you in the Resource name box.
4To enter the type of resource, in the Type box, click the Down arrow, select Work, and then click OK.
5To plan for the availability of three camcorders every workday, click the Max. Units field for Mini-DV Camcorder, click the Up arrow until 300% displays, and then press ENTER.
6To enter additional equipment resources directly in the Resource Sheet, click the next empty cell under Mini-DV Camcorder, press SPACEBAR, and wait as the resource names are typed for you.
7To plan for the availability of four 600-watt lights and stands every workday, select the Max. Units field for 600-Watt Light and Stand, and then click the Up arrow until 400% displays.
8To plan for the availability of two camera booms, select the Max. Units field for Camera Boom, and then click the Up arrow until 200% displays.
9To enter pay rates for one of your equipment resources, select the Std. Rate field for Mini-DV Camcorder, press SPACEBAR, wait as the rate is typed for you, and then press ENTER.
10To enter pay rates for the remaining four equipment resources, in the Std. Rate field for 600-Watt Light and Stand, press SPACEBAR, wait as the rates are typed for you, and then press ENTER.
11Now, to enter a material resource, in the Resource Name column of the Resource Sheet, click the empty cell after Editing Lab, press SPACEBAR, wait as the text is typed for you, and then press TAB.
12To assign this as a material resource, in the Type field, click the Down arrow, select Material from the list, and then press TAB.
13To add a more detailed description of this resource, in the Material Label field, press SPACEBAR, and wait as the text is typed for you.
14To enter a standard cost for each cassette tape, select the Std. Rate field for that resource, press SPACEBAR, wait as the cost is typed for you, and then press ENTER.

Adjusting Working Time for People Resources

1To change the working and nonworking times for individual work resources, click the Tools menu, and click Change Working Time.
2To select a resource, in the Change Working Time dialog box, click the arrow in the For box, and in the list, click Garrett R. Vargas.
3To display the calendar for this resource, in the Select Date(s): box, drag the scroll box down until the calendar for January 2005 displays.
4To set two nonworking days for this resource, in the January 2005 calendar, click 13, hold down the CTRL key, and then click 14.
5To continue, under Set selected date(s) to, click Nonworking time.
6To change the working time of another resource, click the For arrow, click below the scroll box on the scroll bar, and then click Sandra Martinez.
7In the message box that asks if you want to save the changes you made to the resource calendar of Garrett R. Vargas, click Yes.
8To change the working hours of resource Sandra Martinez, in the Select Date(s): box, click M, hold down the SHIFT key, and click Th.
9To change the work hours for this resource, triple-click in the indicated To box, and then, for the purposes of this exercise, press SPACEBAR and the new working time will be typed for you.
10To set a nonworking day for this resource, in the calendar, click the column heading F, and then under Set selected date(s) to, click Nonworking time, and click OK.

Documenting Tasks and Resources

1To enter task notes, on the Project Guide toolbar, click Tasks, and in the Tasks pane, click Link to or attach more task information.
2To select the task to which you want to add a note, in the Task Name column in the Gantt Chart, click Pick locations.
3In the Add Information pane, click Add a note.
4To enter a note, on the Notes tab of the Task Information dialog box, for the purposes of this exercise, press SPACEBAR, wait as the text is typed for you in the Notes box, and then click OK.
5To display the note, in the Indicators column, hold the mouse pointer over the Note indicator, and then double-click the Note indicator, and when the full note displays in the Task Information dialog box, click Cancel to close it.
6To select the task for which you want to create a hyperlink, in the Task Name column, click Hold auditions.
7To insert a hyperlink, in the Add Information pane, click Add a hyperlink.
8To insert a hyperlink, in the Insert Hyperlink dialog box, click the Text to display box, and then press SPACEBAR and the text will be typed for you.
9To insert a Web address, click in the Address box, press SPACEBAR, wait as the address is typed for you, and then click OK.
10Notice that a Hyperlink indicator appears in the Indicators column. To read the descriptive text you typed, point to this indicator, and then, to close the Add Information pane, click Done.
11To switch to the Resource Sheet view to enter resource notes, click the View menu, and then click Resource Sheet.
12To select the resource to which you want to add a note, in the Resource Name column, click Garrett R. Vargas, and on the Standard toolbar, click the indicated Resource Information button.
13In the Resource Information dialog box, click the Notes tab.
14To add note text, click the Notes text box, press SPACEBAR, wait as the text is typed for you, and then click OK.
15To view the note, hold the mouse pointer over the Note indicator in the Indicators column.