Core Training for Microsoft Office Project 2003
Tracking Progress on Tasks
Saving the Baseline of a Project
| 1 | To begin saving a project baseline, on the Project Guide toolbar, click the Track button. |
| 2 | To save the first project baseline, in the Track pane, click Save a baseline plan to compare with later versions. |
| 3 | To finish saving the baseline, in the Save Baseline pane, click Save Baseline, and then click Done. |
| 4 | To hide the Project Guide pane, on the Project Guide toolbar, click the Show/Hide Project Guide button. |
| 5 | To view the task values in the baseline, click the View menu, point to Table: Summary, and then click Variance. |
| 6 | To widen the Start column so that the cells showing pound signs will display a value, in the row of column headers, double-click the line that separates the Start and Finish column headers. |
| 7 | To widen the Finish column so that the remaining cells showing pound signs will display values, double-click the line that separates the Finish and Baseline Start column headers. |
| 8 | To save a second project baseline by using a different method, click the Tools menu, point to Tracking, and then click Save Baseline. |
| 9 | In the Save Baseline dialog box, click the arrow in the box below the Save baseline option, and in the Save baseline list, click Baseline 1. |
| 10 | To save only selected tasks and roll them up to summary tasks, under For:, click Selected tasks, and then under Roll up baselines:, click the To all summary tasks check box, and then click OK. |
| 11 | To clear the project baseline for Baseline 1, click the Tools menu, point to Tracking, and then click Clear Baseline. |
| 12 | In the Clear Baseline dialog box, click the Clear baseline plan arrow, click Baseline 1, and then click OK. |
Tracking How Much Work Is Complete
| 1 | To begin recording the actual work of a project by updating work to the current date, click the View menu, and then click Gantt Chart. |
| 2 | To update the project, click the Tools menu, point to Tracking, and then click Update Project. |
| 3 | In the Update Project dialog box, note that the Update work as complete through option is selected, and then click the arrow in the adjacent date box. |
| 4 | In the January, 2005 calendar, click 10, and then click OK. |
| 5 | To begin tracking the percent complete for tasks, on the Project Guide toolbar, click Track. |
| 6 | To track the progress of each task, in the Track pane, click Prepare to track the progress of your project. |
| 7 | To set how task progress should be tracked, in the Setup Tracking pane, notice that Always track by entering the Percent of Work Complete is selected, and then click Done. |
| 8 | Notice that Project has updated the % Work Complete field to 100% for tasks 2 and 3. To enter the percent of work complete for the next task, click in the % Work Complete field for Pick locations. |
| 9 | To update this task to 100% complete, in the % Work Complete field, point to the Up arrow in the selected field, hold down the mouse button until 100% displays, and then press ENTER. |
| 10 | To view the Gantt bar for a specific task in the Gantt Chart, in the Task Name column, click Develop script, and then on the Standard toolbar, click the indicated Go To Selected Task button. |
| 11 | To change the percentage of work complete for a task by using the Tracking toolbar, click the View menu, point to Toolbars, and click Tracking. |
| 12 | To quickly update the percent complete for another task, in the Task Name column, click Hold auditions, and then on the Tracking toolbar, click the 50% Complete button. |
Entering Actual Values for Tasks
| 1 | To begin recording actual work values, start dates, and duration for some tasks, in the Track pane, click Prepare to track the progress of your project. |
| 2 | To change the tracking method, in the Setup Tracking pane, click Always track by entering the Actual Work Done and Work Remaining. |
| 3 | To apply your changes, in the Setup Tracking pane, click below the scroll box on the scroll bar and then click Done. |
| 4 | To close the Project Guide, on the Project Guide toolbar, click the Show/Hide Project Guide button. |
| 5 | To enter the actual work for a task, click in the Actual Work field for the Hold auditions task, point to the Up arrow and hold down the mouse button until 80 hrs displays, and then press ENTER. |
| 6 | Notice that Project extended the Gantt bar of the task to indicate the longer duration, and rescheduled subsequent tasks. To select a new task to update, in the Task Name column, click the Rehearse task. |
| 7 | To begin entering the actual start date and duration for the task, click the Tools menu, point to Tracking, and then click Update Tasks. |
| 8 | To update the actual start date for the selected task, in the Update Tasks dialog box, under Actual, click the Start arrow, and in the January, 2005 calendar, click 17. |
| 9 | To update the actual duration of the task, in the Actual dur box, click the Up arrow until 3d is displayed, and then click OK. |
| 10 | Notice that Project has updated the Gantt bar for the Rehearse task to display as 100% complete. To update the actual duration for the next task, in the Task Name column, click Shoot video. |
| 11 | To continue updating, click the Tools menu, point to Tracking, and then click Update Tasks. |
| 12 | To record the actual duration of the task as three days, in the Update Tasks dialog box, in the Actual dur box, click the Up arrow until 3d is displayed. |
| 13 | To apply the change, click OK. |